Problem of Too many FS Relations

Rauf KensukMember for 6 years 9 months
Created
2
3
0
Project: Typical Residence House Project  
 
I am preparing a schedule of residence project. Construction contains 17 Blocks and each block has approx. 11 floors. So that too many activities and it s about to get 11.000 activites.   
 
Even i don't want but i use too many "FS relationships" in order to hang the activities in timeline and I know it will cause too many Out-Of-Seqeunce ("OOS").   
 
1st Floor >>FS>> 2nd Floor >>FS>> 3rd Floor  
 
In practical 2nd floor may start without waiting for finishing 1st Floor and that cause "OOS"  
 
To avoid that i m thinking to use 1st Floor >>SS and FF and + LAG: 1st Floor Duration >> 2nd Floor. If 2nd floor starts before finishing 1 st Floor, it will cause a gap as 1st Floor Remaining duration for 2nd Floor activity but not OOS, I think.   
 
Doing SS + FF + Lag, what else may it cause a problem that I can't imagine ?  

Thanks in advance

2 replies

Oldest first
  1. 0
    Rafael Davila ·

    The following article might

    The following article might be of particular interest to users of P6 as out of the box it fails to identify many such occurrences.

    Out-of-Sequence Progress

    Among a few I have the following comments;

    Image-121

    Image-130

    When is Out-of-Sequence not Out-of-Sequence? - A deeper out-of-sequence condition is demonstrated using OOS Act 3. It began as logic allows, immediately following the logical completion of OOS Act 2, so it would appear to not be out-ofsequence. An expanded view of the actual status compared with original logic shows that OOS Act 3 began prior to the finish of Act A and is thus logically out-of-sequence with Act A. No commercial software currently reports this condition as an out-of-sequence start.

    *********************************************************************               

    Spider does not labels activites as out-of-sequence or not out-of-sequence, it is enough to identify broken dependencies.

    If OOS-3 requires some information that is prepared on activity OOS-2 and OOS-2 was finished it can be done even though activity OOS-2 was done out of sequence. lf OOS-3 started before finish of OOS-2 then the link would be broken.

    Spider identifies OOS-2 as having a broken link, OOS-3 as not having a broken link, Spider delays remaining durarion of OOS-2 and OOS-3 after finish of Act-A restoring all broken dependencies still active when option to restore all broken dependencies is selected.

    I wonder if P6 not being able to identify some OOS ocurrences is just a report issue or if it also means it can miss the implementation of retained logic for these ocurrences. 

  2. 0
    Jerome Odeh ·

    Hi Rauf,If only P6 had Soft &

    Hi Rauf,

    If only P6 had Soft & Hard logic features where we can identify preferential and mandatory logic relationships. Unfortunately, the gods at Oracle hardly listen to end-users so are deaf to our features requirements.

    As for your schedule problem, I'd stick to FS relationshiips and change these logics to SS if a successor starts before the predecessor finishes when I enter ACTUALS. Just ensure that your Schedule Basis Memorandum makes it clear which relationships ar soft (preferential) & which ones are hard (mandatory) and update these assumptions during your regular schedule update cycle.

    ===

    jerome odeh

    https://www.plannersplace.com/