Calendar
In the Open Standard
Moutaz AldeibMember for 22 years 9 months
- Created
- 3
- 1
0
Greetings planners,
I have a schedule with calendar six days working from 8:00 a.m to 17:00 applied to all tasks. The dates for the tasks are completely strange for me. for example:
task A: 5 days, the start date is 16 Jan 8:00, it gives me the finish date 21 Jan 9:00
task B: 3 days, the start date is 16 Jan 8:00, it gives me the finish date 19 Jan 10:00
knowing that from 16 Jan to 21 Jan, no holidays or off days.
I am really confiused about the calendar
Regards,
Muataz
3 replies