Hi,

Can anyone tell me if Primavera has a specific cut off date for long range portfolio planning?  I know the system can cope with 10-20 years but am not so sure projecting say 80-100 years plus for full lifecycle portfolio planning.  I ran a few scenarios and the forecast dates appear to be in the past. 

Appreciate any feed back. 

Thanks

 

Simon  

1 reply

Oldest first
  1. 0
    David Kelly ·

    good for all four digit year

    good for all four digit year numbers.