Skip to content

Space in Bar

Moutaz AldeibMember for 22 years 9 months
Created
5
3
0

Greetings Planners

I am updating a baseline schedule, some of the activities that have actual start but not yet completed, their bar after the data date bar is not continous, there is a space between the data date and then the bar for the next period starts.

Is there any explanation for this.

Regards,

Muataz

5 replies

Oldest first
  1. 0
    Jerome Odeh ·

    Moutaz,Most likely the your

    Moutaz,

    Most likely the your calendar start time is 08:00 while your data date time is 00:00

    Check this blog post for details

    https://www.plannersplace.com/blog/how-remove-gaps-after-data-date-primavera-p6

     

    =jerome

  2. 0
    Zoltan Palffy ·

    here is the fix go to bars go

    here is the fix go to bars 

    go to the actual work bar and in the 3rd column (time scale) chneg this setting from Actual bar to Current bar

  3. 0
    Jerome Odeh ·

    Hi Zoltan,Won't changing

    Hi Zoltan,

    Won't changing Actual Work setting to Current Bar make it show progress beyond data date?

    Jerome

  4. 0
    Santosh Bhat ·

    You have retained logic

    You have retained logic running through the predecessors of that task, check the relationships have been upheld as you've enterered the actual dates.

  5. 0
    Zoltan Palffy ·

    it may well be ahead of the

    it may well be ahead of the planned or baseline schedule 

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?