RESOURCES DISTRIBUTION WHEN UPDATING

Antonello PumiliaMember for 21 years 1 month
Created
1
4
0

Hi all,

I allocated revenues in a non labor resource assigned to activities. Now, we manually input the monthly revenues we forecast so that the curve for the remaining units (money) is not calculated by the software, maybe applying a resources curve, but it is set by ourselves according to our knowledge of what will happen.

So we have, for instance, 

    Data date   
 BudgetActualRemainingapr-21mag-21giu-21lug-21
Activity1002080535,00,040,0

Now, when I update, even by giving to apr-21 the exact number as planned (i.e.),

the precise distribution of the remaining units is messed up and recalculated, and it becomes:

    Data date   
 BudgetActualRemainingapr-21mag-21giu-21lug-21
Activity1002080525,324,525,3

How do I preserve, my original distibution?

thanks everyone that can help!

antonello

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    assign a resource curve

    assign a resource curve 

Log in or join to reply