Change in Budgeted Units

Jithin KambhikanamMember for 15 years 6 months
Created
3
3
0

Hello Everyone,

 

I exported a schedule, rerouce loaded it and imported it back to the P6.

 

After checking some activity I saw that I for got to add some other resource for the same activity. But when I add this resource through Primavera it changes the existing allocated reource. I do not want that to happen. Please advice me on how to tackle it.

 

Example :

Activity A had a resource at First: Carpenter - 20 Hrs .

 

I missed adding Labor, so when I added it. It distributes the 20 Hrs, Now Carpenter = 10 Hrs, Labor = 10 Hrs

 

Thanks

Jithin

3 replies

Oldest first
  1. 0
    Rodel Marasigan ·

    Hi Jithin,You need to change

    Hi Jithin,

    You need to change the Resource assignment calculation when adding or removing resources. On menu select Edit--> User Preferences. When the pop-up window User Preferences click Calculation tab and select Preserve Units, Duration, .... see below:
    Resource-Assignment-Option

  2. 0
    Jithin Kambhikanam ·

    Thanks Rodel, A good info.

    Thanks Rodel,

     

    A good info.

  3. 0
    Rodel Marasigan ·

    You're welcome, happy to

    You're welcome, happy to help.