Change in Budgeted Units
In the Open Standard
Jithin KambhikanamMember for 15 years 6 months
- Created
- 3
- 3
0
Hello Everyone,
I exported a schedule, rerouce loaded it and imported it back to the P6.
After checking some activity I saw that I for got to add some other resource for the same activity. But when I add this resource through Primavera it changes the existing allocated reource. I do not want that to happen. Please advice me on how to tackle it.
Example :
Activity A had a resource at First: Carpenter - 20 Hrs .
I missed adding Labor, so when I added it. It distributes the 20 Hrs, Now Carpenter = 10 Hrs, Labor = 10 Hrs
Thanks
Jithin