Maintain Multiple Baseline with 1 step

Rami LoukaMember for 6 years 10 months
Created
2
2
0

Hi Guys,

I am dealing with window analysis with a lot if windows/projects/updates to compare, so here is my question:

How can I maintain multiple baselines to project in 1 step?? 

Again: I want to maintain two or three project to my current opened project in 1 step (1 click), is there a way sto select multiple projects and maintain them as baseline in 1 step?

 

Thanks for the help

2 replies

Oldest first
  1. 0
    Rodel Marasigan ·

    Hi Rami,That is not possible

    Hi Rami,

    That is not possible because the database only accept one at a time maintaining baseline and the same with assigning Baseline.

  2. 0
    Zoltan Palffy ·

    its a 2 step process you can

    its a 2 step process you can compare up to 3 baselines

    1st select project maintain basleine then select assign baseline 

    do this for up to 3 baselines 