What would cause P6 to NOT use the default units/time when assigning a resources?
In the Open Standard
Alex GarciaMember for 10 years
- Created
- 3
- 3
0
When assigning resources, P6 isn't using the default units/time to populate the budgeted units. For example, our resources are set to 8h/day. So, when we assign a resource to an 8 day activity, the default budgeted units should be 64h, with 8h/day. But, it's loading 264h @ 33h/day. What would drive this, and how can it be fixed?