P6's crazy calendar

John ReevesMember for 13 years 5 months
Created
2
1
0

I date vs duration complications I cannot figure out.  I assume it is from the contractors's calendar.  I am going to import others to see.  But also, will all time be calculated correctly if I put the hours per time period at 8dy 40 wk 172 mo, 2000 a year.  It is odd p6 makes you do this because each month is a different amoun 30/31 dys month etc. Is there a source as to a good basic setting for 5 dy wk , 6dy wk, 7dy wk.  

2 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    no lazy calendar lazy

    no lazy calendar lazy scheduler 

    make sure that the start of the project TIME is correct

    make sure that the data date TIME is correct.

    Make sure that on any constraints the TIME is correct

  2. 0
    Zoltan Palffy ·

    no lazy calendar lazy

    no lazy calendar lazy scheduler 

    make sure that the start of the project TIME is correct

    make sure that the data date TIME is correct.

    Make sure that on any constraints the TIME is correct

Log in or join to reply