No variance column to compare in Current File Actual finish to Baseline finish - isn't that the most important item?

John ReevesMember for 13 years 5 months
Created
2
2
0

No variance column to compare in Current File Actual finish to Baseline finish - isn't that the most important item?  -  Am I wrong, I could in P3, it seems crazy that P3 was/is better in many ways....

2 replies

Oldest first
  1. 0
    Rodel Marasigan ·

    Variance Column is always

    Variance Column is always available in P6. It's under Duration group. See below:

    Variance-Column

  2. 0
    Zoltan Palffy ·

    Rodel has the answer

    Rodel has the answer