Skip to content

Owner looked at schedule and asked why there were late dates on items with Actuals - what do you say? what do you do?

John ReevesMember for 13 years 5 months
Created
2
2
0

Owner looked at schedule and asked why there were late dates on items with Actuals - what do you say? what do you do? - because it is true, it does not make sense.  I assume people copy the dates to a column and delete them in the udf column - but sounds like a huge hassle -  is there an easier way?  is this something Oracle should fix - I guess I always just ignored it.

2 replies

Oldest first
  1. 0
    Rodel Marasigan ·

    If the activity is complete

    If the activity is complete there is no remaining late date. If the activity is in progress with float then it has remaining late dates.

  2. 0
    Zoltan Palffy ·

    if an activty is complete it

    if an activty is complete it still has an original late date even thought this is no longer part of the total float calculations. However if activities are in progress its has a remaining late finsh date. For activites that are COMPLETED there is not and Remaining Late Finish date so it might be best to show the remaining late finish date column. 

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?