Reporting for P6 using Oracle BIP

Casey FMember for 10 years 4 months
Created
1
2
0

Hi All, 

When attempting to report from P6 via Oracle BIP for some reason I am unable to get all of the projects.  I am wondering if there is a security setting or something that is holding these projects back from being reported.  

For Example:

If I have multiple projects across multiple OBS bands, I can currently only get projects from 1 OBS band.  Even when just pulling in the project name into Oracle BIP report. 

If I set the project id to project "12345" that project will come in but not project "6789".  When all things appear to be equal. 

 

All projects appear to be summarized, status of Active, Nothing is checked out, I'm not seeing major difference. 

 

Any guidance or thoughts would be greatly appreciated!

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    try opening all the projects

    try opening all the projects at the saem time for the reports that you want. 

    hold the control key down to select multiple projects.

Log in or join to reply