Multiple Baseline Units

Huss PSMember for 4 years 2 months
Created
4
4
0

Hi All,

 

I have 2 baselines and i need to compare the Labour units for both with the current schedule. 

How can i get the labour units for both of these baselines?

From below snapshot under "Units" both of the highlighted options are giving the same value.

 

TIA.

4 replies

Oldest first
  1. 0
    Huss PS ·

    (No subject)

  2. 0
    Huss PS ·

    (No subject)

  3. 0
    David Kelly ·

    The colums BL project Labour

    The colums BL project Labour Units and BL1 project labour units. You have to declare a Project and  Primary (BL1) baseline in the Assign Baselines dialogue

  4. 0
    Zoltan Palffy ·

    you can have up to 3

    you can have up to 3 different baselines