Skip to content

Differences between Dates FIELDS

Abbas RajabpourMember for 4 years
Created
6
2
0

Hi All

 

I was just reading the primavera help and came across three different fields:

Start

Planned Start

BL Project Start

I have a question about the following picture, why is there difference between " Planned Start" and " BL Project Start"? Don't they come from the same source which is Project Baseline?

Aren't they the same?

Why is there difference between them? There are some activities that they are exactly the same ( I mean planned start and BL Project Baseline, and there are activiteis where they are different.)

Thanks for your help.

6 replies

Oldest first
  1. 0
    Rodel Marasigan ·

    Project Baseline Start - The

    Project Baseline Start - The current start date of the activity in the project baseline.  This setting is control by the Earned Value Calculation setting under Admin Preference. When earned value is using planned dates then the start will be set to the activity's planned start date.  When earned value is using current dates then the start will be set to the planned start date until the activity is started, then set to the actual start date.

    Plan Start - The date of activity is scheduled to begin. This date behaviour is control in the settings at Project module under Calculation Tab, Activities-> Link Budget and At Completion for not started activities and Reset Remaining Duration and units to Original. This date is computed by the P6 application but can be updated manually by the P6 user. This date is not changed by the P6 application after the activity has been started.

    Start - The current start date of the activity.  Set to the activity remaining early start date while the activity is not started, and the actual start date once the activity is started.

  2. 0
    Abbas Rajabpour ·

    Thanks Rodel for your reply,

    Thanks Rodel for your reply, the thing is as you said for the project baselne start, there are two scenarios:( I don't have access to admin preferences, as it is locked by the company)

    1- Budgeted values with planned dates:

    BL Project start date = Planned Start 

    But as you can see in the photo, this is not happening, so this scenario is wrong.

    2- Budgeted values with current dates:

    A : If not started ==> Planned start = BL Project dates ( As you can see in the photo, Site Demobilisation is not started and the planned start date is 22-Nov but the PL Project Start is 7-Jul.

    B: If started( Completed or in progress) ==> BL Project Start = Actual Start( Again you can see for activity : Temporary Works, which is in progress, BL Project Strt is 15-Nov-21 and planned Start is 10-May -22 and Start is 09-May-2022.

     

    So I am missing something?

  3. 0
    Rodel Marasigan ·

    Hi Abbas,Project Baseline

    Hi Abbas,

    Project Baseline Start Date is the assign Project Baseline and not the Plan date of the current project that is why it is different. If you create a copy of the current project and assigned as Project Baseline and the setting is Budgeted Value with Planned Date on Earned Value calculation then it should be the same. If the current project is updated after the Project Baseline is assigned, some date might already change during the update and running the schedule (F9).

  4. 0
    David Kelly ·

    Abbas,I have very little peer

    Abbas,

    I have very little peer group envy, but I wish I had written these books by Paul Harris:

    https://www.eastwoodharris.com/primavera-p6/

     

    excellent, and on the desk of every Senior Planner I know. That is quite a lot.

    The complete guide to dates in Primavera was written by another expert, Ron Winter, you can download it here:

    https://www.ronwinterconsulting.com/Understanding_P6_Dates.pdf

     

  5. 0
    Santosh Bhat ·

    I second getting Ron Winter's

    I second getting Ron Winter's paper about this, explains it all. 

  6. 0
    Peter Holroyd ·

    Hi Abbas, P6 has about 50

    Hi Abbas,

     

    P6 has about 50 date fields and 50 ways of displaying those dates (not counting different national calendars) which are all defined by Paul E. This tells you whether it is a calculated or input field.

    Difficulty I have is I have never read a paper which tells you which dates are used by which analysis or report!

    Keep asking questions

    Peter

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?