SS & FF Relationship

Huss PSMember for 4 years 2 months
Created
8
1
0

Hi All,

I have a scenario where i have to use SS & FF relationship together. Problem is it's not working.

Objective:

A1170 strats when A1130 Starts

A1170 finished when A1160 finished

 

 

I tried adding LOE activitiy (A2690) and put a relationship with A1170 but this didn't work. I think i have to put both SS & FF relationship with LOE activity but this didn't work.

 

Did the same for WBS summary but same happenend.

Any suggestions please.

 

thanks 

8 replies

Oldest first
  1. 0
    Rodel Marasigan ·

    The only way is to use LOE as

    The only way is to use LOE as per below:

    A1170 - LOE Activity
    Predecessor  A1130  SS
    Successor A1160 FF

  2. 0
    Rafael Davila ·

    https://boyleprojectconsultin

    https://boyleprojectconsulting.com/tomsblog/2017/11/06/constructing-level-of-effort-loe-activities-in-primavera-p6/

  3. 0
    Huss PS ·

    Thanks, But i need to assign

    Thanks, But i need to assign resoureces to it. Not sure if that will work with LOE and might need to reosurce level it too in future.

  4. 0
    Huss PS ·

    Thanks, But i need to assign

    Thanks, But i need to assign resoureces to it. Not sure if that will work with LOE and might need to reosurce level it too in future.

  5. 0
    Huss PS ·

    Thanks, But i need to assign

    Thanks, But i need to assign resoureces to it. Not sure if that will work with LOE and might need to reosurce level it too in future.

  6. 0
    Rodel Marasigan ·

    Of course you can use LOE for

    Of course you can use LOE for resource loading. It is a logical way of resource loading such as prelims, engineering, constuction supports, equipment usage and or summary level of resouces.

  7. 0
    David Kelly ·

    LoE activities are terrific

    LoE activities are terrific for 'overhead' costs and resources, and even better for collecting timesheet data that has not got any activity ID information. You cannot level the resources.

  8. 0
    Huss PS ·

    Thanks all for recommendation

    Thanks all for recommendation but this activity is not an overhead. Its is task dependent and can be on CP with resource assigned to it.. The tricky part is, it dpendent on the 2 activities above it. So, in simple terms i need to relate it with the earliest start & latest finish of either of the above 2 activities.

Log in or join to reply