Database Malformed error

Phil BedfordMember for 10 years 3 months
Created
4
2
0

Morning folks,

I have a Primavera P6 v21.12 standalone SQL Lite database which I was working on yesterday, however this morning I have gone to open P6 and it is giving me a "database disk image is malformed"

Thankfully I did create an xer backup last Friday, so still have the main project available which I have imported to a new DB, however I'd really like to be able to access the corrupt DB.

Anyone know of a way this can be repaired?

Thanks,

Phil B.

4 replies

Oldest first
  1. 0
    Rodel Marasigan ·

    If you are using SQL Lite and

    If you are using SQL Lite and you know where the location folder of SQL Light database is (ex: *.db), try to create a copy of the database and rename it. Then try to edit the database configuration of the rename copy of SQL Light database and connect it. Sometimes it works.

  2. 0
    Phil Bedford ·

    Thanks for the suggestion.I

    Thanks for the suggestion.

    I have made a copy of the corrupt DB and renamed it.

    Went to connect but sadly had the same error.

    Thanks again.

  3. 0
    Phil Bedford ·

    .

    .

  4. 0
    Santosh Bhat ·

    There is a complicated set of

    There is a complicated set of steps that Oracle says is a workaround, not a solution. Go to the ORacle support site and find this Doc ID.

    Error 'Database disk image is malformed' When Attempting to Open a Project, or 'Catastrophic error' When Logging into P6 Standalone with an SQLite Database (Doc ID 2021648.1)