Multiple Databases

Huss PSMember for 4 years 2 months
Created
6
4
0

Hi All,

Need to combine two p6 databases into one database. Both are different users


first user has P6 v21.12 database.
Second user has P6 v22 database.

Need to merge the first user database into the second.

I have tried going into "Edit Database settings" > "Add a connection to existing standalone database". 

6 replies

Oldest first
  1. 0
    David Kelly ·

    This is not trivial.You will

    This is not trivial.

    You will have to export the projects from one and import into another.

    BUT

    XER format does not export baselines. Restoring baselines, making an XER file from them, importing into target database and then demoting them is very labour intensive and error prone.

    The  XML format is extremely CPU intensive, very inefficient, and can only deal with small numbers of activities before you get JavaHeap errors. It does take baselines.

    Best of luck!

  2. 0
    David Kelly ·

    This is not trivial.You will

    This is not trivial.

    You will have to export the projects from one and import into another.

    BUT

    XER format does not export baselines. Restoring baselines, making an XER file from them, importing into target database and then demoting them is very labour intensive and error prone.

    The  XML format is extremely CPU intensive, very inefficient, and can only deal with small numbers of activities before you get JavaHeap errors. It does take baselines.

    Best of luck!

  3. 0
    Huss PS ·

    Thanks David.Can i add first

    Thanks David.

    Can i add first user's database as additional to the second users' ?

    I am think of working with 2 databases where i can select any one that i am planning to work on.

  4. 0
    David Kelly ·

    Operating with two versions

    Operating with two versions of the P6 database on one machine is 'simple' if you use a virtual machine environment. I use Oracle's 'Virtualbox' on my dual Xeon 64GB RAM monster, but is hard work.

    In general one P6 database version with the P6 Windows client MANDATORY for that database version.

    I much prefer v22 to v21

  5. 0
    Huss PS ·

    Thnaks David.I found the

    Thnaks David.

    I found the solution with the help of oracle support and little bit of tweaks.

    Here it goes..

     

    Issue:

    first user has P6 v21.12 database.
    Second user has P6 v22 database.

    Both machines were separate. Couldn't merge these databases as not possible so, will be using 2 databases and switch between the 2 as needed.

    Solution:

    -Launch P6 V22

    -select "Edit Database configuration"

    -select "Add" on left top

    -select "Driver type" from drop down menu. Select appropriate option. I selected "P6 Professional Standalone (SQLite).

    -select "Add a connection to an existing standalone database" while on this step you can also rename under "Database Alias"

    -select location of the P6 Database file you want to connect to.

    -click Test

    -click Save

    -Run P6

    Note : If it gives an Error "The application and database version do not match" or Error "DATABASE VERSION MISMATCH" at P6 Professional Login then after clicking OK in the error window another window pops up prompting the user to upgrade the existing database.  Click Yes to upgrade.

  6. 0
    Zoltan Palffy ·

    you can run 2 different

    you can run 2 different versions they just have to be installed in different locations. One icon or shortcut points to version

    P6 v21.12 database and the other icon or shortcut points to the P6 v22 database.