P6 Histograms - Baseline Budgeted Units VS. Current Schedule Actual Units
- Created
- 6
- 5
Hi everyone, my first post here!
As the title says, my goal is to obtain S-Curves within Primavera that compare the budgeted units of activities using the baseline dates to their actual units using the current schedule dates.
I've read that "Resource Usage Profile" does not contain/can't display baseline data. Even if it is possible, I'm not sure that budgeted units are attached to the baseline.
Is there any way to do this withing Primavera that I'm missing?
In case this can't be done, what would be the best way to achieve this by exporting data to excel?
Thanks in advance.
Kind regards,
Chema
6 replies
Oldest firstLog in or join to reply