Skip to content

How to determine Total Float Calculation for Critcal Path

Kt G23Member for 11 years 3 months
Created
1
5
0

Hi Guys

I am reviewing a contractor P6 programme that has 0 Total Float as it is due to finish before the 'Must Finish By' date. It is therefore showing no Critical Path when scheduled using the Default setting 'Total Float less than 0d'. Can anyone advise what would be best way to determine a Total Float value for the Critical Path calculation? I've tried the longest path setting instead but it's not valid as activities are constrained.

Any advice would be much appreciated.

Thanks

1 reply

Oldest first
  1. 0
    Jithin Kambhikanam ·

    Go to Project - Click on the

    Go to Project - Click on the Project - In the bottom go to settings

    In settings go to Define critical Activities and mention the Total Float less than or equal to = which which would be considered as Critical

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?