Claim digger

Martin CordonMember for 9 years 10 months
Created
1
3
0
Can claim digger be set to only return results for a certain date range?

1 reply

Oldest first
  1. 0
    Pratap Dinahar ·

    Not that I know of. You can

    Not that I know of. You can as a workaround, use Vlookups on dates in the entire Claim Digger report based on the date ranges you need. (assuming the report is in Excel)