Particular Resource assignment automatically in Primavera among the group of Resources
- Created
- 0
- 6
Hi
Need your support here.
This is related to Manufacturing planning works.
Activity A - Machining operation - 15 days
Activity B - Machining operation - 10 days
Activity C - MAchining operation - 20 days
Activity D - Machining operation - 25 days
Activity E - Machining operation - 5 days
Activity F - Machining operation - 5 days.
All activites were independent. We are having two resources say LATHE 1 and LATHE 2. Is it possible in Primavera , assigning the resource for the above activities ( either LATHE 1 or LATHE 2 ) will be done automatically depends on the resource loading/activity operation to get better result. (Shortest Project Duration).
Thanks in advance
Ram
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?