just started to learn about Project Managment and reading about PERT/CPM.

why do u divide by 6? and why do u multiply by 4?

Expected Time:
t = (a + 4m + b)/6

3 replies

Oldest first
  1. 0
    Steven Oliver ·
    Where

    a = pessimistic duration

    4m = 4 * probable duration

    b = optimistic duration

    generally accepted "rule of thumb". You could equally propose your own method.

    (((a+b)/2)+m)/2) for instance

  2. 0
    Charleston-Joseph Orbe ·
    Hello,

    This is related to the theory of probability.

    The graph generated is a bell shape.

    The equation is similar to mean average.

    I hope you understand and recall your mathematics or higher algebra, differential calculus, intergral calculus, engineering mathtmatics or any subject related to mathematics.

    Cheers,

    Charlie
  3. 0
    Pmkb . ·
    It’s a weighted average. The 4 and 6 are related to each other in that you have 4 parts of one element and 1 part each of two other elements for 6 total parts. The equation could just as easily have 6/8 instead of 4/6 if the probable estimate was deemed to have a higher weight.

    I do not know why 4/6 is generally used as opposed to 6/8, 10/12 or any other weighting factor.

    Stacy
    Project Management Knowledge Base

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?