S-curve and Weightings

Joshua JuanezaMember for 20 years 1 month
Created
1
2
0
I am trying to refresh my memory about planning, since I underwent a surgery. I can’t remember now how to create an S-curve using Primavera Project Planner ver. 3.1 or P3. Also, I have trouble recalling how to use WEIGHTING in loading for resources. Could somebody help me recall everything?...PLS. I BADLY NEED TO RECALL..because I need to go back to my previous job as Planner. Thanks in advance

1 reply

Oldest first
  1. 0
    Jawad Al-Nimri ·
    Dear,

    you must load resources & costs to your schedule, giving them the unite rates, then you will go to veiw / resource profile, choose all then display costs. it is that simple. i think you meant something else, right???