Generating Progress Curves in MS Excel
In the Open Standard
William SargentMember for 19 years 8 months
- Created
- 0
- 5
0
I’m looking to create a dynamic spreadsheet in MS Excel to double check P3 and do other work offline.
Specifically, I am looking to create a spreadsheet where I can enter in a total duration, remaining duration, a curve type and total number of units (manhours, euros, etc.) so that I may then be able to calculate the remaining values by period.
For example:
I have a ten month duration for manhours where durations are also in months. For this task I have allocated 100k manhours. I have chosen to model the based on a bell shaped distribution and have alocated the manhours as follows:
Month: qty
1: 1k
2: 3k
3: 8k
4: 15k
5: 23k
6: 23K
7: 15k
8: 8k
9: 3k
10: 1k
Halfway through the project, I progress the activity. I want to forecase the remaining distribution of 75K in accordance with the "trailing" end of the distribution curve which would yield the following values:
Month: qty
5: 23,630
6: 23,630
7: 15,411
8: 8,219
9: 3,081
10: 1,027
I can make these calculation manually, but as I stated above I’m looking for a MS Excel templete where I enter or select the appropriate variables and then view the result.
The curves that I am looking for a the standard curves in P3.
If anyone has any ideas, it would be greatly appreciated.
Cheers,
Specifically, I am looking to create a spreadsheet where I can enter in a total duration, remaining duration, a curve type and total number of units (manhours, euros, etc.) so that I may then be able to calculate the remaining values by period.
For example:
I have a ten month duration for manhours where durations are also in months. For this task I have allocated 100k manhours. I have chosen to model the based on a bell shaped distribution and have alocated the manhours as follows:
Month: qty
1: 1k
2: 3k
3: 8k
4: 15k
5: 23k
6: 23K
7: 15k
8: 8k
9: 3k
10: 1k
Halfway through the project, I progress the activity. I want to forecase the remaining distribution of 75K in accordance with the "trailing" end of the distribution curve which would yield the following values:
Month: qty
5: 23,630
6: 23,630
7: 15,411
8: 8,219
9: 3,081
10: 1,027
I can make these calculation manually, but as I stated above I’m looking for a MS Excel templete where I enter or select the appropriate variables and then view the result.
The curves that I am looking for a the standard curves in P3.
If anyone has any ideas, it would be greatly appreciated.
Cheers,
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?