Level 2 Schedule

Mary FolsomMember for 23 years 4 months
Created
3
2
0
What would your definition of a level 2 schedule?

3 replies

Oldest first
  1. 0
    Andrew Podolny ·
    http://www.hud.gov/offices/cpo/evms/clause.pdf

    Check the bottom of page 4.
    Regards,
    Andrew
  2. 0
    Karim Mounir ·
    Mary,

    checkout this file:
    http://www.planningengineers.org/knowledge/techniques/peo_technique3.pdf

    Regards,
    Karim
  3. 0
    Andrew Donlan ·
    Hi Mary

    My response below :

    Level 2 : This normally is a Project Integrated Schedule - which includes all work broken down into manageable packages, where responsibility, time, cost and resources are embedded in the detail and interfaces between the work packages and functions identified.(Typically 250-300 activities depending on project size of course!)

    Best Regards
    Andy