what all types floats are there,

Vikas ViswamMember for 18 years 6 months
Created
7
4
0
what all types floats are there, I Heard 4 types,
But used only Total and Free. If any body knows other types plse xplain

Vikas Viswam
Dubai

7 replies

Oldest first
  1. 0
    Chris Oggham ·
    Hi Vikas,

    If you use the Wideman Glossary, you should find all the information you need.

    Chris Oggham

  2. 0
    Charleston-Joseph Orbe ·
    vikas,

    basically only two: free float and total float

    but our english peers invented a new english term: terminal float

    mike has another meaning for float: noah ark floating
  3. 0
    Chris Oggham ·
    Hi Vikas,

    Since Charlie raised it, you can find out all you ever wanted to know about Terminal Float by clicking on the link. Don’t worry about Charlie’s crack about the English, he finds them a convenient scapegoat for anything he doesn’t like.

    Chris Oggham
  4. 0
    Ashutosh Nema, PMP ·
    HI Vikas,
    These are the floats available
    Total float
    Free flaot
    Independent Float

    Ashutosh Nema

  5. 0
    Andrew Flowerdew ·
    Just want to wind Charlie up: (apologises Charlie)

    Some English peers have now invented more terms ,(well a while ago actually):-

    First there was

    Free and Total float

    Then came

    End or Terminal flaot

    And now

    External and Internal float

    What next???????????????????????
  6. 0
    Raja Izat Raja Ibrahim ·
    sure must be ice cream float...haha
  7. 0
    Raja Izat Raja Ibrahim ·
    sorry guys,
    to me if u cant get the correct sequence and the activities is not in complete link forget about to use float calculation...my advise. its will come worst result.