Closing Cavity Walls

James YoungMember for 18 years 4 months
Created
3
4
0
Morning all,

Has anyone got any production outouts for closing cavity Walls?

Regards,

James

3 replies

Oldest first
  1. 0
    Anoon Iimos ·
    i believe the question is not answerable without any details (in an engineers point of view)
  2. 0
    Baris Baris ·
    Even though this is non-technical answer,

    For trying to help you, i have just found these typical sections about insulation of cavity walls?

    http://www.plymouthfoam.com/building_products/duraspec/images/cavitygeneralimage.jpg

    http://www.achfoam.com/ACH/media/images/Sheathing/Cavity%20Wall2.jpg
  3. 0
    Mike Testro ·
    Hi James

    Wessex estimating item GJ002 Closing Cavities not exceeding 75mm wide:

    102.5 Facing Brickwork:
    at jambe or end of wall 0.40 lab hours per m
    at sill 0.55 lab hours per m
    at top of wall 0.30 lab hours per m

    As I advised earlier - get the disc from RICS bookshop.

    Best regards

    Mike Testro