Scheduling Skycrapper

Claude ManelMember for 18 years
Created
9
4
0
Hello everyone,
Since we reach the 90% of the building works, some of our big boss tells us that "perhaps we don´t need to shcedule the rest of the works til the end"
Personally i think that its completely the opposite, NOW is when we need to know where we are and wich are our targets to manage our time in the right way. Perhaps as a stakeholder I cannot see the truth
Can I be wrong? why don´t anyone tell me (us) some exit work wich near scheduling (or not..)
Thx a lot

9 replies

Oldest first
  1. 0
    Anoon Iimos ·
    don’t know, perhaps they don’t want to end the project or they don’t have any intention to pay the remaining 10% (usually it’s the retention!).
  2. 0
    Charleston-Joseph Orbe ·
    Claude,

    Some of your boss are dead wrong.

    the remaining 10 % should be schedule in more details.

    We just don’t know the glitch or hitch that may happen to the remaining 10 % that may impact on the schedule completion.

    So, please tell some of your boss, that it is very important to continue with the planning and scheduling including project control till completion of the project.

    Cheers,
    Charlie
  3. 0
    Sandy Matheson ·
    So is this a high level toilet project?
  4. 0
    Mike Testro ·
    Hi Claude

    Please ignore Sandy - we have all made spelling errors - you will have to understand British scatology to get the "joke".

    Meanwhile the finishing activity that is rarely planned correctly is the M&E test and commissioning period.

    This always comes last and is often ignored or under resourced.

    (unless of course you are dealing with Charlestons "Wild Air" which requires an interim commissioning)

    I am not an M&E engineer but I have picked up the basics over the years and I ensure that my programmes have sufficient time to finish correcly.

    Best regards

    Mike Testro
  5. 0
    Steven Oliver ·
    I have never worked on a project that got easier towards the end, usually quite the reverse.
  6. 0
    Claude Manel ·
    Thanks to everyone, as I thought we must schedule til the end, and then do the commitment with or without planning, cause I was telling this % only for works.
    Thanks a lot again
  7. 0
    Mike Testro ·
    Hi Claude

    You seem to have drifted away from reality in your last thread.

    Alawys rember the planners golden rule.

    the first 90% of the work takes the first 90% of the time

    The last 10% of the work takes the other 90% of the time.

    Think and replan.

    Best regards

    Mike Testro
  8. 0
    Claude Manel ·
    Thanks, Mike
    I was joking actually, thats my way of express the kind of unknoledge of my directors.
    I afraid you cant know what the reality on shcedulling in Spain is.
    When you say Primavera (in Spain we use this word to say spring) everybody even INSIDE some engeneeers or architects tells you what kind of flours you prefer...
    The distance between Spain and the rest of the world in this way is decades
    Sorry now crying on your shoulder....
    Thx a lot
    C
  9. 0
    A D ·
    I thought it’s 80:20 principle