remove links between % completion and budegted quanty
In the Open Standard
Bilal TirmiziMember for 17 years 10 months
- Created
- 4
- 3
0
Dear all,
i want to monitor my project in the manner illustrated in the following example, i need help on which auto cost rules to change.
suppose activity is of excavation and scheduled days are 10 and budgeteg manhous(resource) is 100 hrs
At the end of 5 days the situation is like i gave RD(5 days) and percent completion of the task is 30% and the resource used is like 65 hrs
my question is that i want to keep the PCT, RD and actual quantity not linked with each other ....so which rules of auto cost i shall change
i want to monitor my project in the manner illustrated in the following example, i need help on which auto cost rules to change.
suppose activity is of excavation and scheduled days are 10 and budgeteg manhous(resource) is 100 hrs
At the end of 5 days the situation is like i gave RD(5 days) and percent completion of the task is 30% and the resource used is like 65 hrs
my question is that i want to keep the PCT, RD and actual quantity not linked with each other ....so which rules of auto cost i shall change
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?