Skip to content

Production Rate for Steel Erection

JV AmandeMember for 18 years 7 months
Created
23
4
0


guys, any1 knows production rate for steel erection and cladding erection..

thanks.. pls. e-mail me at maraksot_2004@yahoo.com.

thanks.

23 replies

Oldest first
  1. 0
    Samer Zawaydeh ·
    Dear JV,

    It depends on the size of project that you have and the construction method that you are using.

    Please specify what type of project you have in order to assist you more:

    a. Pre- Engineered Buildings.
    b. Structural Steel
    b.1 Extra Heavy
    b.2 Heavy
    b.3 Medium
    b.4 Light Weight
    c. Tanks
    d. Vessels
    e. Pipe Racks
    f. Space Trusses
    g. Tensile Structures
    h. Poles
    i. Towers

    With best regards,

    Samer
  2. 0
    JV Amande ·


    Dear Samer,

    Thanks and i appreciate you for your immediate response.

    I want to know the production rate in Steel Erection and Cladding Erection.. perhaps this will fall to Steel Structure?

    I want to know how many manhours per TONS of steel can be erected...

    and how many square meters of roof and wall sheets i can install in one hour?

    do you have any idea sir?

    thanks and hope to hear your idea again.

    thank you.

    JV
  3. 0
    Samer Zawaydeh ·
    Dear JV,

    Please let us know where is the project and at what height you are installing, what is the lifting mechanism that you are using.

    Give us a little bit of a description about the system that you want to install.

    1. Brackets + Panels
    2. Purlins+ Mesh + Insulation + Corrugated Sheets.
    3. etc.

    With kind regards,

    Samer
  4. 0
    A D ·
    It seems that u r talking about pre-engineered buildings.

    In PEB, steel erection productivity is not measured in Tons and there r separate productivity rates for girders, crane beams, roof purlins and mezzanine deck.

    For roof cladding, it depends on the system to be used. If it is standing seam, then productivity can be as low as 250Sqm per 8 hours of job, but for conventional sheeting, it can go as high as 450 Sqm per 8 hours of job.

    With insulation, it will drop by 30-35%.

    If the sheets are site rolled, u can hav maximum length (20/30/40m) and so, the productivity will be on higher side. Can reach upto 800 Sqm per 10 hours of job

    For liner panels, it depends on height. Howver, for 10-12m height, it can be somewhere around 80-100 Sqm for 8 hours job.

    For wall cladding, it depends upon the length of the wall sheet but will always less than the roof sheeting.

    Do let us know more details like size of teh building, span, ht and others to be more specific with the production rates.
  5. 0
    JV Amande ·

    Dear Samer;

    Thank you for your idea about this, i think..

    I can use this as reference for some of my estimate works.

    Anyway.. I ask about the production rate of steel erection and cladding erection so that i have basis for my accomplishment report.

    I think, in terms of the steel structure, i can compute the % accomplishtment in terms of weight of the building.

    That is why, i asked how much weight i can install in 8 hours. Do you have any idea if their is standard computation for this?

    My idea about this is that, i can compute my % accompl. in terms of wt. for steel structures (such, columns, girts, rafters, eave-struts and so other steel frame.)

    for cladding.. i just want to know how many sq.m. can be installed in an hour. (in terms of area)

    Thanks for your idea Samer.

    This is just part of my studies.. Thank you.
  6. 0
    Samer Zawaydeh ·
    Dear JV,

    You are most welcomed. The more you ask the more you understand.

    I would like to know what you are studying.

    At the same time, please note that the Structural Steel is calculated per ton and the cladding is calculated per m2.

    Usually you have a tracking report from birth to installation for each piece of steel. This is tracked from the raw material stage, fabrication, treatment, dispatching, storage at site, and erection. Quality Control records are tracked for each piece and for each stage depending on the Inspection requirements.

    The productivity rate depends on the location, environmental factory, and others as explained before.

    With kinds regards,

    Samer
  7. 0
    JV Amande ·


    Dear Sir Samer;

    Thank you for your immediate kind response to my query.
    I am studying about Steel Erection. I would like only to be equipped with ideas and knowledge about (Steel Structures) for career development.

    Thank you Sir. Your ideas has help me understand more about the Steel Structures.


    Thanks

    jV
  8. 0
    Mike Testro ·
    Hi Samer

    I have been watching this thread from a distance and I am very impressed with your contribution.

    If you are tracking every steel member from factory - shipping - site storage and erection - then how do you link the steel beam to the activity on the programme in respect of location and time.

    I have always advocated bottom up planning but this seems to be going too far.

    Best regards

    Mike Testro
  9. 0
    Samer Zawaydeh ·
    Dear Mike,

    The structural steel models are created based on the requirements of the clients. These are analyzed and designed. Subsequently, detailing takes place and each piece is marked. Shop drawings are generated and issued to shop for fabrication and treatment.

    The shipping is done on priority basis or as per client request. For large projects, each piece has a bar code sticker for identification. It is received at site and stored using bar code scanner as well.

    Once erection takes place (assuming that you project plan is about construction at site) then each piece that is installed at site is reported back as being installed.

    The range for the number of pieces varies a lot; For structural steel you might have up to 20,000 pieces, whereas, for pressure vessels you might has a few as 1 piece with a weight of 1000 tons.

    On large plants the range for structural steel can be as much as 60,000 tons that needs to be erected within 1-2 years. Others, you might have 2000 tons (30 pieces) that must be erected during a shut down peried of 3 weeks. This is project dependent. It is bottom up most of the time.

    With kind regards,

    Samer
  10. 0
    Mike Testro ·
    Hi Samer

    I understand the process that you have described and use of a handheld bar code reader (like in my mobile phone) will track the stockpile and installation of each steel member and this could be scheduled on a spreadsheet.

    Such a spreadsheet could also link to the bar chart activity which would have a resource in steel tonnes fixed per day.

    Daily progress could be measured against that planned by updating steel fixed with the planned production.

    Used with a detailed bottom up plan that would work well.

    Thanks again.

    Mike Testro
  11. 0
    Samer Zawaydeh ·
    Happy New Year Mike,

    What you said is correct. Usually steel manufacturers have in-house tracking. Big companies have their own tracking systems that are part of the Conditions of Contract. Suppliers and Erectors have to use these online tracking systems inorder to get their reporting done and invoicing complete.

    Having the piece mark as an activity is not a standard procedure. I recommend that the Engineer on the project understand the construction sequence and come up with his/her Own Program of Works with the approval of the erection crews.

    With kind regards,

    Samer
  12. 0
    Matthew Edwards ·
    Dear samer & Mike

    For installation, I use the production rate of 20 pieces of steel per tower crane per day. Cladding - depends on the type.

    Regards

    Matthew Edwards
  13. 0
    Samer Zawaydeh ·
    Dear Matthew,

    It depends on the project, experience of the crew and the equipment that the Contractor has available at site.

    At one site we had 1 lift of 120 tons per week for the Tower Crane! On a 12000MT project. Whereas, for a light weight structure, we completed 300m2 (two and half floor) in 20 days.

    Environmental factors; location, wind speed, time of year also has an adverse effect on the production rate. It must be factored in the Program of Works, otherwise, you will have delays.

    For Structural Steel at heights, a lift specific plan must be submitted and approved before work can proceed. The basic idea would be to maximize the safe weight to lift with the maximum number of pieces.

    With kind regards,

    Samer
  14. 0
    Sajid Jaffery ·

    Can somebody please provide

    Can somebody please provide me productivity rates for Waterproofing, Cladding, Steel Panels, roofing and Detail excavation for building. Pls. also advise if there is any online resource available for conversion of quantities too.

     

    Thank you,

  15. 0
    Mushtaque Ali ·

    Dear AllKindly Provide me

    Dear All

    Kindly Provide me Productivity of Roof & Wall Cladding.

    Where in Roof Space frame + Roof sheet etc.

    Wall Cladding height 10 mts and Glass Cladding.

     

    Thanks in advance

  16. 0
    Sakela Sifuba ·

    Hi All Can anyone assist,

    Hi All

     

    Can anyone assist, currently doing a programme for a structural steel high rise building about 9 floors, average floor area  3200m2, hieght between floors 3.6m

    Columns - 24kg/m2 (2.4 tons / column) - about 62 columns per floor size PG 310x300x16x40

    Beams- 65kg/m2 (2,5 tons per beam)

    about 130 members per floor.

    Had meetings with the contractor that will do the erection and they saying they can take 5  working days per floor, did the programme resourced it accordingly as per the outputs they gave me and it came to 55tons/day

     

    Is this possible or rather can this be achived, 55 tons/day? with 5 teams

    planning to have two tower cranes on site with a 60m long jib max lifting wieght  2.5 tons at 55 metres.

     

    Thanks

    Sakela.

  17. 0
    Abdelaziz Elsaid ·

    Dear all        kindly

    Dear all 

           kindly provide me with productivity of Concrete items in infrastructure projects

           my mail  engabdelaziz49@gmail.com

     

    Best regards

          Abdelaziz Elsaid 

     

  18. 0
    Abdelaziz Elsaid ·

    Dear all        kindly

    Dear all 

           kindly provide me with productivity of Concrete items in infrastructure projects

           my mail  engabdelaziz49@gmail.com

     

    Best regards

          Abdelaziz Elsaid 

     

  19. 0
    Abdelaziz Elsaid ·

    Dear all        kindly

    Dear all 

           kindly provide me with productivity of Concrete items in infrastructure projects

           my mail  engabdelaziz49@gmail.com

     

    Best regards

          Abdelaziz Elsaid 

     

  20. 0
    Jyles Baris ·

    Please send production rate

    Please send production rate of steel structure here: jylesronnbaris@gmail.com

     

    Very much appreciated.

    Thanks!

  21. 0
    Alex Rooker ·

    Kindly provide me with the

    Kindly provide me with the production rate of steel structure here geometry dash

  22. 0
    Ma Tessa Altavano ·

    Hi Matthew Edwards, is it

    Hi Matthew Edwards, is it true that for erecting peb frames you have erected 20 pcs of steel columns in 1 Tower crane in 8 hours work? If yes, how many Manpower did you use? Thanks. I need help to derive unit cost of labor for the stee works. Please hope you can help.

  23. 0
    Haithem Abdelrahman ·

    Good Day, Please advise me,

    Good Day,

     

    Please advise me, how many tons of steel structures (average of light, meduim & heavy) can be produced with 1700m2 workshop area & what is the neccessary machinary i can start with ?

     

    Thanks

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?