Labour Units mismatch in p6
In the Open Standard
Almas AhmedMember for 16 years 8 months
- Created
- 1
- 3
0
Hi all,
I received a P6 schedule from my subcon loaded with manhours.When I imported the .xer file there is mismatch of toal labour units.However I am able to find out why this mismatch is and this is due to the resource’s (manhours) units/time which is zero in my system.
I tried with the global change to multiply all the budgeted units with 8 but still could not match with the total labour units as in the subcons schedule.
The strange thing is that when I multiply the roll-up totals with 8 manually I am getting the right answer but when done the same multiplication by 8 with a global change I am not getting the total.
I appreciate your opinions on this.
regards,
Almas
I received a P6 schedule from my subcon loaded with manhours.When I imported the .xer file there is mismatch of toal labour units.However I am able to find out why this mismatch is and this is due to the resource’s (manhours) units/time which is zero in my system.
I tried with the global change to multiply all the budgeted units with 8 but still could not match with the total labour units as in the subcons schedule.
The strange thing is that when I multiply the roll-up totals with 8 manually I am getting the right answer but when done the same multiplication by 8 with a global change I am not getting the total.
I appreciate your opinions on this.
regards,
Almas
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?