Successor
In the Open Standard
V KuttyMember for 16 years 10 months
- Created
- 7
- 2
0
Hi,
I have a question.
We are using negative lags for example design to be finalised 60 days before Manufacture of First unit.
Manucture unit one FS(-60) Finalise design
Here the Predecessor of Finalise design is Manufacture unit one. What could I use as its successor so that Float values are good and real.
Thanks,
Vijay
I have a question.
We are using negative lags for example design to be finalised 60 days before Manufacture of First unit.
Manucture unit one FS(-60) Finalise design
Here the Predecessor of Finalise design is Manufacture unit one. What could I use as its successor so that Float values are good and real.
Thanks,
Vijay
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?