Skip to content

Recovery Schedule

Amro AhmedMember for 17 years 9 months
Created
2
1
0

Dear All,

What the best method to issue Recovery Schedule   using baseline and update are already exist in step

2 replies

Oldest first
  1. 0
    Rafael Davila ·

    If you are into trouble

    If you are into trouble probably original schedule was no good. At times in order to recover you will have to re-schedule your plans with completely new logic. Let the team that will be responsible to implement it be free to make the necessary adjustments, if major surgery is required then let it be.

    The fixation with Baseline Schedule some owners and delay analysts have can do more harm than good to the scheduling and managing of the job.

  2. 0
    Amro Ahmed ·

    it,s available to  fix actual

    it,s available to  fix actual dates as baseline from Global Changes then add Remaining Works but i want to get the best detailed procedure to do that?

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?