The performance % complete is not equal cost % complete

Yahya AtefMember for 9 years 5 months
Created
1
4
0

I make revised plan for my project but there is a problem the performance % complete does not equal the cost % complete ?

 

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·

    Performance % Complete:The

    Performance % Complete:

    The Performance % Complete is used to compute earned value and may be based on the Activity % Complete, the 0/100 rule, the 50/50 rule, or other techniques, depending on the method used to calculate the earned-value percent complete for the activity's Work Breakdown Structure (WBS). The Performance % Complete specifies the percentage of the activity's planned value that has been earned so far. On the other hand, the cost % complete is calculated based on the actual costs entered in the Actual Cost field, including labor, non-labor, materials, and expenses. To match it, you can adjust the cost value to align with the earned value.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?