Hello,
When dealing with Terminal Float in a schedule where the Contract Date is left for the Contractor to propose, a good rule of thumb is to allow some buffer to account for uncertainties and changes. Terminal Float is the amount of time available at the end of the project, allowing for any final adjustments, delays, or unforeseen issues without affecting the overall completion date.
Assess Project Complexity: For simpler projects, 5-10% of the project duration as Terminal Float is often sufficient. For more complex projects, where uncertainties are higher, you might increase this to 10-20%.
Industry Standards: Refer to industry standards and past projects of similar scope. This can provide a benchmark for the appropriate amount of Terminal Float based on similar conditions.
Risk Management: Factor in potential risks and their impact on the schedule. If there are high risks, allowing more Terminal Float helps accommodate these uncertainties.
Thanks,