Finish date is being calculated from data Date
In the Open Standard
Andrew FrancisMember for 13 years 1 month
- Created
- 4
- 4
0
Dear all,
I am unsure if this is a "glich" but I have noticed that if my DD is say 16 October 23, and I have an 20 d activity that should start on 11/3/ 24 and finish 10/4/24 ( I dont want to change the DD as activities are still fluid and being added but some have started and i have not been able to set a baseline yet). If This activity actually started on the 11/3/24 A and then I F9 the schedule - the fiinsh date is showing as the 13 November 23. ( It looks as though it has added 20D to the DD. ?
Is this correct or a glich ?
4 replies
Oldest firstLog in or join to reply