baseline update - past activities
In the Open Standard
Rafael DoblasMember for 11 years 7 months
- Created
- 6
- 3
0
Hello all,
Wanted to get some guidance on this:
We are in the middle of a project. We started working on an extension of time case with the client but took forever to have that accepted. In the meanwhile, we missed some milestones as per the original baseline. Those activities are now in the past. Are we supposed to change the baseline for past activities as per the new extension of time?
thanks!
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?