Skip to content

baseline update - past activities

Rafael DoblasMember for 11 years 7 months
Created
6
3
0

Hello all,

Wanted to get some guidance on this:

We are in the middle of a project. We started working on an extension of time case with the client but took forever to have that accepted. In the meanwhile, we missed some milestones as per the original baseline. Those activities are now in the past. Are we supposed to change the baseline for past activities as per the new extension of time?

 

thanks!

6 replies

Oldest first
  1. 0
    Patrick Weaver ·

    The general rule is no

    The general rule is no retrospective changes to either the baseline or the progressed activities. The situation shown is what was current at the time. 

    My recommendation would be for any milestone that occured after the delay, but before the EOT was granted simply note that subsequently an EOT of XX days has been grated reducing / elimineting the delayed completion. 

    When you rebaseline the schedule, you can either insert activities at the pont of each delay with a duration equal to the approved EOT (of if the delay was general insert non-working days in the calendar). But this rebaselined schedule should only be used fo reporting going forward. The EOTs are not an excuse for recasting the schedule baseline without agreement from the client. 

    A lot depends on the terms of your contract. 

    For more on this see: https://mosaicprojects.com.au/PMKI-SCH-014.php#Process6 

  2. 0
    Khawaja Ahtisham ·

    Hi All I have query that I

    Hi All I have query that I have recieved Main Contractor Program of works as first program during the execution of project with Baseline dates and Updated/Revised dates together,Program of works also carrying -36 days TF, I am claiming this program with udated dates as a Baseline program for us with responsibility of -ve TF under Main Contractor... Is my claim justified !!!or there is better way to handle thesituation !!!! The program of works fil is provided in pdf format only. Regards Khawaja
  3. 0
    Khawaja Ahtisham ·

    Hi All I have query that I

    Hi All I have query that I have recieved Main Contractor Program of works as first program during the execution of project with Baseline dates and Updated/Revised dates together,Program of works also carrying -36 days TF, I am claiming this program with udated dates as a Baseline program for us with responsibility of -ve TF under Main Contractor... Is my claim justified !!!or there is better way to handle thesituation !!!! The program of works fil is provided in pdf format only. Regards Khawaja
  4. 0
    Khawaja Ahtisham ·

    We are in the middle of a

    We are in the middle of a project. We started working on an extension of time case with the client but took forever to have that accepted. In the meanwhile, we missed some milestones as per the original baseline. Those activities are now in the past. Are we supposed to change the baseline for past activities as per the new extension of time?

    If I have understood correctly, I would like to know that why you want to make changes in Baseline program for the past activities ,instead of submitting the update EoT including the mile stone missed , if it is due to reason attributable to Client.If the impact of the updated EoT is more than ,what was submitted before than you are entitled for the resubission.

    Al though it also depends on nature of your claim ,if it was full and final or Interim claim.

    Rgds

  5. 0
    Khawaja Ahtisham ·

    If I have understood

    If I have understood correctly, I would like to know that why you want to make changes in Baseline program for the past activities ,instead of submitting the update EoT including the mile stone missed , if it is due to reason attributable to Client.If the impact of the updated EoT is more than ,what was submitted before than you are entitled for the resubission.

    Al though it also depends on nature of your claim ,if it was full and final or Interim claim.

    Rgds

  6. 0
    Zoltan Palffy ·

    no you NEVER change a

    no you NEVER change a baseline doing that is like palying football and alwasy moving the gola post you can never get a touch down. 

     

    If you missed the milestones they should be re-forecasted based on your updated schedulle 

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?