Activities Spanning More Days than it should in a Primavera P6 Schedule

Karim SaadiMember for 1 year 4 months
Created
3
5
0
Hi Dears After having created and updated a CPM schedule using Primavera P6 you notice that some 1 day activities are spanning 2 days. How could this be possible? Although you are scheduling your schedule in days Primavera behind the scenes actually utilizes the hour and minute functions of a day within the program to perform the forward and backward passes. If you look a 1 day activity you may find that a 1 day duration activity actually spanning 2 days. It shows planning to start on 1 day but is forecasted to finish on the next when it should start AND finish all on the same day. SAADI.K

3 replies

Oldest first
  1. 0
    Patrick Weaver ·

    The problem is almost always

    The problem is almost always in the calendars - different number of hours in a day, different start times in a day, or simply a predecessor finishing half way through a day.  

  2. 0
    Zoltan Palffy ·

    it has to do with times tunr

    it has to do with times tunr on your times go to edit uses preference and turn on the times. 

    also in there set the duration dispaly to 2 decimals as you may have soem activites that are not whole days.

    any start milestones the TIME should be set to 8:00 am or the start of the day for the calendar that it is on.

    any finish milestones the TIMES should be set to 5:00 PM or the latest time for at the end of the day for the calendar that this milestone is on.

    also any start constraints the TIME should be set to 8:00 am or the start of the day for the calendar that this activity is on

    also any finish constraints the TIMES should be set to 5:00 PM or the latest time for at the end of the day for the calendar that this activity is on.

    also ALL actual start TIMES should be  set to 8:00 am or the start of the day for the calendar that this activity is on

    also ALL actual fininsh TIMES should be set to 5:00 PM or the latest time for at the end of the day for the calendar that this activity is on.

  3. 0
    Emerald Associates APAC ·

    Hi All, An innovative product

    Hi All,
     
    An innovative product line of Oracle Primavera enhancements and add-ons unique to Emerald Associates. Our clients come to us with Primavera problems, and we create tools to solve them.Emerald Tools - Primavera Enhancements and Add-Ons

    You may join our free webinars and register ahead of the schedules - Webinar Schedule - Primavera P6 Add-On Tools and Safran Risk

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?