Percentage Progess checking

Forum GuestMember for 17 years 8 months
Created
7
3
0
Hi Friends

I am new to this website.
Well I would like to ask that is it possible to theorytically check the overall percentage progress given by the system after you have fed the actual start dates and percentage progress in the schedule

suppose the system gives me 10 % overall progress.How can i check it.

7 replies

Oldest first
  1. 0
    Steven Oliver ·
    To what "system" are you referring ?
  2. 0
    Bernard Ertl ·
    Progress can be either a measure of time or effort (manhours). Since time and effort are not linear across the span of a project, I prefer and recommend that you measure progress in terms of manhours.

    You can only qualify the overall percent complete if you can qualify the degree of accuracy in the estimating. Even then, you are assuming that the remaining schedule will stay within the margin of error recorded up to that point in time. This may or may not be a safe assumption.

    Bernard Ertl
    InterPlan Systems Inc. - Project Management Software, Project Planning Software
  3. 0
    Ronald Winter ·
    If you are using P3, there is a simple way to note project percent complete (using remaining durations.) Just run a CPM report. At the bottom (around the fifth line from the bottom, I believe,) there will be a listing of Project Percent Complete. Good luck!
  4. 0
    Forum Guest ·
    Using duration as weighing factor, you can check by computing manually using the formula (Sum of OD - Sum of RD)/Sum of OD.

    OD - Original Duration
    RD - Remaining Duration

    For resource units the formula is AQ/BQ

    AQ - Actual Quantity
    BQ - Budgeted Quantity

    For cost, the formula is AC/BC

    AC - Actual Cost
    BC - Budgeted Cost

    You can check all these data by printing reports.

  5. 0
    Sagar Agrawal ·
    Thank you all for the reply

    Well what I want to calculate is the overall percentage progress of the total project which P3 gives us when we summarize the whole project

    Cause for that we are relying on the system.

    I agree there could be weightage factors like Cost,Qunatity
    but say that for a simple Schedule with no resource planning how would you calaculate the overall progress or how does the system calculate the overall summarized progress.
  6. 0
    Mary JoAnn ·
    what do you mean by "system"???
  7. 0
    Bernard Ertl ·
    I think by "system" he means the software (P3 in this case).

    [quote]for a simple Schedule with no resource planning how would you calculate the overall progress or how does the system calculate the overall summarized progress.[/quote]

    Without resource planning, you are limited to measuring time. This is not a useful measure IMHO.

    However, for each task, you can calculate:

    Hours Elapsed / Hours Scheduled * 100 = Percent Complete

    When calculating percent complete as a measure of time, each task is weighted the same, so average the percents complete across all tasks to find the total.

    Bernard Ertl
    InterPlan Systems Inc. - Project Management Software, Project Planning Software

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?