Dear Planners,

I would be grateful to you, if you could guide me on how to establish a link between P3 schedule dates to Autocad layout in order to show ES and EF dates for each I-Beam placement in the Autocad layout. So that i could avoid of manualy updating scheduled dates for the I-Beam Layout in Autocad if there is any changes in P3 schedule.

Regards
Daya

3 replies

Oldest first
  1. 0
    Mehdi Rashidi Alangeh ·
    Dear Dhandapany,
    I think autocad soft is not stable for your issues.
    You must use the macro in Excel soft. because excel has a dynamic link with P3.

    regards
  2. 0
    Morteza Jafari ·
    I heard there is possible to make a Link between P3 and cad, my friend worked in engineering company and he had made a soulation for it if I will find and ask him.
  3. 0
    Mk Tse ·
    As far as I know, it only work on AutoCAD latest version.

    Predefine all text boxes which hold date value. One text box for each. Build a link table, Activity ID against text box name, 1 to 1. run a AutoCAD macro, fill the text box value by the linked ACT IDs date.