Skip to content

critical path.

Dayanidhi DhandapanyMember for 23 years 7 months
Created
18
2
0
Which relationship like FS or FF (with positive lag) is the best practical way to use in order to form a critical path? in my opinion all activities must have finish to start relationship if we have enough detailed break down. During the absence of such details(delay in awarding sub-contract works)what could be done? i leave this question to our fellow planners.....................

What is the easiet way to group multiple critical paths in P3. Other than Navigating through driving relationships and assign some custom codings corresponding to each critical paths..............

18 replies

Oldest first
  1. 0
    Bernard Ertl ·
    Critical Path Method - A technique used to predict project duration by analyzing which sequence of activities has the least amount of scheduling flexibility. Early dates are figured by a forward pass using a specific start date and late dates are figured by using a backward pass starting from a completion date.

    There are other definitions, but this one is appears to be the most common.




    "Classic CPM theory would calculate the early start date from the project’s notice to proceed or data date. Many schedulers consider the classic theory the proper calculation method for the determination of early start and early finish, The issue revolves around the selection of which float values to use in precedence schedules and proper relationship rules. Start float, activity float, and finish float can vary dramatically, with complex relationships. However, under classic scheduling theory, there can be one early start float, multiple activity floats for different portions of the activity, and one finish float." - excerpted from Construction Delay Claims by Bramble and Callahan

    IOW, calculate early starts, early finishes and late finishes in one direction (each).




    To answer your question, it may be instructive to look at the differences between ADM (arrow diagramming method) and PDM (precedence diagramming method). ADM and PDM are not logical equivalents. PDM can fully describe ADM networks, but the complement is not true. PDM contains constructs that can not be adequately described by ADM (and thus, are of debatable application in a strict critical path method schedule, IMHO).
    • FS (finish to start) - logical equivalent in ADM (predecessors end node = successors start node)
    • SS (start to start) - logical equivalent in ADM (dummy task connects predecessors start node to successors start node)
    • FF (finish to finish) - no exact equivalent in ADM. Can be expressed in ADM with a dummy task connecting the predecessors end node to the successors end node, however, this does not produce the same result as a FF tie in PDM because ADM logic networks drive relationships in one direction. The resulting ADM schedule will not force a Gantt chart to display the tasks as completing at the same time, just that the successors succeeding tasks are dependent upon both.
    • SF (start to finish) - no logical equivalent in ADM. ADM logic networks drive relationships in one direction.
    • LAGS (FS & SS) - logical equivalent in ADM using dummy tasks with durations equal to the lag span.
    • LAGS (SF & FF) - no logical equivalent.

    The critical path method was created with ADM. Straying from logical equivalents of that construct may lead to schedules that do not meet the classic definition of a critical path method schedule.

    Bernard Ertl
    InterPlan Systems Inc. - Project Management Software, Project Planning Software
  2. 0
    Bernard Ertl ·
    For those who are interested, a side discussion on the whether or not a PDM SS relationship can be modeled equivalently in ADM is ongoing in this thread:

    ADM / PDM SS relationships thread

    Bernard Ertl
    InterPlan Systems Inc. - Project Management Software, Project Planning Software
  3. 0
    Luca Basile ·
    I do not think is useful to coding the critical path/s as it/they can change from daily to monthly bases.
    It depend from the kind of programme.
    Take in consideration a shut-down/maintenanece programme, that run in few days/weeks and is monitored at least once day. So every day you change the coding,to identify the critical path?

    The critical path you mentioned have TF zero or are "iper-critical" one with TF<0?
    If the TF is less than 0, each iper-critical path will have it representative TF, so You can filter or organize on it.
    Pay attention if You are using a multicalendar programme, sometimes the critical activities seat on the longest path!

    You can use also the RA applications. If You identify an activity of the critical path, there is a tools that is telling you all its predecessor and successor.

  4. 0
    Mehdi Rashidi Alangeh ·
    Dear my friends,
    I think this item is old technique.
    Are there any technique ( such as crtitical group method or ... ) in the Pm?
  5. 0
    Luca Basile ·
    Can You give me same idea how to do with P3, and where to find some material to read on it?

    Thanks
  6. 0
    Darrell ODea ·
    critical path.

    You Wrote,
    Asking a question which you have answered.
    FS, SS & FF Relationships are the most practical way to find a CP.
    In identifying CP & groups of CP, if you use a filer which identifies total float as less than or equal to 0.
    --------------------------------------------------------------------------------
    Which relationship like FS or FF (with positive lag) is the best practical way to use in order to form a critical path? in my opinion all activities must have finish to start relationship if we have enough detailed break down. During the absence of such details(delay in awarding sub-contract works)what could be done? i leave this question to our fellow planners.....................

    What is the easiet way to group multiple critical paths in P3. Other than Navigating through driving relationships and assign some custom codings corresponding to each critical paths..............
  7. 0
    David Watters ·
    Luca

    To determine Critical Path on Primaver, you must specify all activites with total float less than 1. Specifying activities with total float less than 0 will only bring up those activities that are super critical, ie are busting the end date

    Cheers
    Dave W
  8. 0
    Vladimir Liberzon ·
    If resources, financing or supplies are constrained then traditional critical path does not make sense. We use the notion of Resource Critical Path consisting of activities that have zero resource constrained total float. This float is calculated when not only forward but also backward pass takes into consideration resource constraints. RCP is the same as Critical Chain if to add financing and supplies constraints to Critical Chain definition. This technique is used in Russia since 1993, long before Critical Chain approach was suggested. RCP can consist of activities that are not linked with each other.
  9. 0
    Luca Basile ·
    Dear Vladimir I find the spider project on internet.
    I give a look at the resource CP.

    Is similar a resource leveling, when I have resource constrain in quantity and/or time frame.
    Just You consider like priority the resoruce, but this is always. I have always to identify the key resoruce and then
    level on it or them.

    As well I find the power point slide about your new software. There is any demo available to be downloaded?


  10. 0
    Vladimir Liberzon ·
    Dear Luca,
    Spider Project Demo can be downloaded from http://www.spiderproject.ru/spider_e.shtml<
    And I advise to read presentations and papers that are presented at http://www.spiderproject.ru/publ_r.shtml at the bottom of the page (in English). In these presentations the concept of Resource Critical Path (RCP) is discussed and some examples are presented.
    RCP is calculated by levelling resources not only on forward but also on backward pass. As the result you will receive activity floats that are calculated taking into consideration resource constraints. These floats can be used! Activity total floats calculated by American packages are not feasible because these packages do not level resources on a backward pass. RCP consists of activities with these resource constrained floats less than specified amount (usually zero, defined by user).
    There are many other useful and unique features in Spider Project desribed in some presentations at this site.
    Please pay attention that Spider Project optimizes resource constrained schedules and thus they are usually shorter than produced by other software due to better resource utilization. Besides you can level not only by resource constraints but also by financial and supply constraints.
    Please don’t hesitate to ask any questions you may have.
    Best Regards.
  11. 0
    Luca Basile ·
    I give a look at all the material.
    But if I well understood the package is making a resoruce levelling taking in consideration only the max resoruce constrain (availability in time). And this mean 99% of the time delay the project.
    Sometimes is mandatory to complete the project in time, as the penalties can be bigger than hire more people or plant for some periods.
    What I saw P3 can also making levelling schedule taking like major contrain the project completion and trying to accomodate the resoruce to produce less overload possible.

    I try to do the example in P3, and the results are matching, with exception for the total float estimation.
    How are You estimating it?

    Is great that the duration is based on the productivity.
    But something similar is possible to do also in P3, when I have a resoruce driven resoruce.

    But what I really appreciate is the opportunity to have different Wbs set up, as my need can be different from the Client or from other departments. As well I can want to have a Wbs function or product oriented for different report pourpose.

  12. 0
    Vladimir Liberzon ·
    Luca, in Spider Project (like in P3) you can choose which resources to level. For others the package will calculate requirements.
    Spider Project calculates expenses and revenues, you can simulate penalties and thus you are able to estimate what decision is the best - to use more resources or to pay penalties.
    Next time we will include in our Demo sample projects for which Spider Project schedule will be shorter than produced by P3 and other packages, Spider Project optimizes resource constrained schedules. The example you tried is too simple and other packages produce the same results.
    Spider Project calculates real feasible floats taking into account resource constraints not only on forward (like other packages) but also on backward pass. These floats can be used without damaging project duration.
    Resource driven duration in P3 is not similar to productivity usage. Adding resources you shorten activity duration but you can not define different productivities for different resources, you cannot define resource productivities for typical activities (norms) and create references.
    There are other useful and simple features - possibility to set any number of cost components (not the same as cost accounts), to use different currencies for different cost components, to create any number of cost centers (sum of expenses by defined set of components), to level by financial and supply constraints (revenue and supply simulation).
    Another thing I suggest to try is skill scheduling (we call it resource assignment pools). And risk simulation too - this thing is very useful.
    I will send you a couple of sample projects illustrating these features. Sample project in Demo illustrates our approach to risk simulation and management by success probability trends.
    Regards,
    Vladimir
  13. 0
    Vladimir Liberzon ·
    Luca,
    please write me a letter to spider@mail.cnt.ru.
    I will send you back the examples.
    Vladimir
  14. 0
    Bernard Ertl ·
    Sorry to drudge up an old thread, but I wanted to clarify my original post to this thread. I realized that there is in fact a logical equivalent in ADM for PDM FF & SF ties.
    • FF (finish to finish) - Can be expressed as a dummy from the predecessor’s end node to the successor’s start node with a duration equal to the successor’s duration * -1.
    • SF (start to finish) - Can be expressed as a dummy from the predecessor’s start node to the successor’s start node with a duration equal to the successor’s duration * -1.
    Unless a software system is designed to assist the scheduler by keeping the durations correct through updates automatically, this would be a nightmare to maintain in ADM.

    I hereby acknowledge my previous mistake and concede that since a PDM schedule can, in fact, be modeled with ADM, all PDM schedules should be compatible with the critical path method. Why didn’t someone correct me earlier?

    Bernard Ertl
    eTaskMaker Project Planning Software
  15. 0
    Ronald Winter ·
    Becase, Bernard you are only looking at an un-statused baseline schedule. PDM operates differently from ADM when status is applied, especially when the actity is in-progress.
  16. 0
    Bernard Ertl ·
    Ron, I based my conclusions above based upon the descriptions of the PDM and ADM calculations described here. The descriptions of the calculations for ES, EF, LS, LF are independent of baselines, progress handling, etc. The differences you describe are dependent upon application specific implementations of the calculations IMO.

    Bernard Ertl
    eTaskMaker Project Planning Software
  17. 0
    Ronald Winter ·
    The article that you quote is an excellent one – perhaps the best one available. Everyone should have this paper and refer to it. Unfortunately, it is still deficient and even incorrect. It uses the CPM calculation method that I have come to term, “Aggie Method” and described in a published article in the Cost Engineering journal of AACEi. I have posed a version of this article (“How to Befuddle a College Professor without Really Trying”) on my website at http://www.ronwinterconsulting.com/published.htm. I believe that Microsoft Project uses this method.

    Primavera (in all of its incarnations) does not use this method. They use the method called the “AACEi Method.” To see a quick difference, compare your hand calculations to a similar schedule in P3. Be sure to look at the work days. You will see that they are different. No matter how simple your example, if you look, you will see differences in workdays for every activity.

    Getting back to your original statement. Your ADM examples do not match PDM. ADM cannot note the start of any activity, only the finish. Your definition depends upon the finish of the predecessor activity to logically start your Start-to-Start successor. It does not take into account that the successor ADM activity may not have actually started. It does not consider that there may be multiple predecessors to the original successor activity.

    Finally, status is not an “implementation consideration.” The data (or status) date must be taken into account if you want the schedule to model reality. The article does not mention using calendars (especially multiple calendars.) It does not address interruptible relationships (which is similar but different from the activity splitting mentioned.) Without status, you cannot begin to address the complexities of computing the CPM with out-of-sequence progress.

    Modern CPM is much more complicated that even the college professors know. Only a handful of engineers understand the complexities of a complete CPM system (and they mostly are working under confidentiality agreements!) It is time that more people became involved discussing these issues, as you are doing here. Keep up the good work!
  18. 0
    Bernard Ertl ·
    Unfortunately, it is still deficient and even incorrect. ... To see a quick difference, compare your hand calculations to a similar schedule in P3....
    We discussed this in the CPM thread. As I explained in my last post there (and quoting from your paper), the algorithms produce the same schedules (calculated dates). The difference is only in where the offset is handled.

    Getting back to your original statement. Your ADM examples do not match PDM. ADM cannot note the start of any activity, only the finish. Your definition depends upon the finish of the predecessor activity to logically start your Start-to-Start successor. It does not take into account that the successor ADM activity may not have actually started. It does not consider that there may be multiple predecessors to the original successor activity.
    Please define what you mean by "note the start of an activity". We discussed the ADM/PDM start to start (SS) constructs in the ADM Software thread and I’m still convinced that your argument is not congruent with the definition of the ADM calculations (see below for further clarification).

    Finally, status is not an “implementation consideration.” The data (or status) date must be taken into account if you want the schedule to model reality. The article does not mention using calendars (especially multiple calendars.) It does not address interruptible relationships (which is similar but different from the activity splitting mentioned.) Without status, you cannot begin to address the complexities of computing the CPM with out-of-sequence progress.
    As you mentioned, resource leveling, disjoint calendars, etc. are not considered in the definition of the ADM & PDM calculations (in the referenced book or any text that I am aware of). They are extensions of the defined calculations and there is no standard for handling/calculating them. Their implementation in any given software application will be set according to the software engineer’s algorithm(s). As such, they are not really germane to a discussion on scheduling that is limited to ADM & PDM definitions IMO.

    Modern CPM is much more complicated that even the college professors know. Only a handful of engineers understand the complexities of a complete CPM system (and they mostly are working under confidentiality agreements!)
    I have worked on the CPM engine in our ATC system for several years. I think I’m pretty well aware of the complexities of programming a complete CPM system.

    I’m guessing that Mr. Liberzon is also in that group. Perhaps he will weigh in with his thoughts.

    It is time that more people became involved discussing these issues, as you are doing here. Keep up the good work!
    Cheers Ron. I agree wholeheartedly and appreciate your part in the discussions.

    Bernard Ertl
    ATC Professional Shutdown / Turnaround Management System

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?