Resource/Cost Loading in P3 based on LS and LF

Louie DucutMember for 22 years 10 months
Created
4
2
0
I want to make a tabular report for the cost and resource loading based on late start and late finish. Can somebody help me.

4 replies

Oldest first
  1. 0
    Zq qz ·
    kABAYAN,
    JUST GO TO THE FF MENU:
    TOOL , TABULAR REPORTS, RESOURCE, TABULAR THEN ADD.....
    IN THE TIMESCALE SELECT THE OPTION YOU WANT.

  2. 0
    Forum Guest ·
    Salamat kabayan...
  3. 0
    Michael Byrne ·
    Louie,

    I have experienced these problems before in trying to develop late data curves through dumping my data into excel. What I found to work, was to create a copy of my schedule offline (call it LATE or whatever you want), and then run a global change changing all of the early starts to late starts, and all of the early finishes to late finishes. Then simply run your reports as normal (early data is now late data)

    Good Luck,

    Michael
  4. 0
    Forum Guest ·
    thanks so much Michael, that’s correct, because I’ve asked the Primavera System and they answer the same.

    Good luck.

    Louie