Disappearing Activities

Joshi NirajMember for 21 years 8 months
Created
8
2
0
When I put 100% progress, early start and early finish dates dispappear and bar also diappear


plz tell me a method that at 100% progress , no bar disappear and dates will show remain show in the column

its very urgent.

thanks

8 replies

Oldest first
  1. 0
    Jaco Stadler ·
    Hi Joshi
    Have you put in actualy start & Finish dates.

    Cheers
  2. 0
    Bernard Ertl ·
    It might help if you identified what software you are using.

    Bernard Ertl
    eTaskMaker Project Planning Software
  3. 0
    Brent Hursey ·
    Are you sure your time scale is set up in a manner that allows you to see the dates you are entering? Try scrolling the timescale graph. Again it may depend upon the scheduling tool. But this sounds like something that can be remedied easily with a little more information.
    Good Luck!
  4. 0
    Raj Maurya ·
    If you are using P3, certainly ES & EF vanished once it is done (100%). I suggest you to format your actual progress bar to see it in bar area after giving progress. I guess in actual bar format you did not tick to show it? If you want to see ES & ES finish bar save as target before updating.
  5. 0
    Shahzad Munawar ·
    Joshi

    Have you got corrected copy of your schedule which I sent u on 22/3/2005, confirm me.

    The error in your programmes was only that your assigned successor and predecssor to one activity was incorrect. That is the reason the loop was showing in your programme.

    Now, its Ok and workable.
  6. 0
    Philip Jonker ·
    Hi guys,
    instead of giving bull, give a direct answer, Joshi, you need to input the actual dares, this is important in terns of history abd if you are a learner, record history
  7. 0
    Ravi Potwar ·
    Joshi,
    Did You Resolved ? if not ,give me call 0506248202
  8. 0
    Sukumaran Subaramaniyan ·
    Check the filter. If your view shows only current activities with 0% or % in progress, try to use All Activities filter.

    If not, go to organize and remove all the setup under Activity Data Item / WBS and view the schedule as a Classic Schedule Layout. Once completed, you can view the 100% completed activities.

    Refresh the schedule and define the Activity Data Item / WBS again. You shall be able to view the activities again