Suspension of work
In the Open Standard
Moosa AliMember for 21 years 6 months
- Created
- 5
- 2
0
My doubt is regarding suspension of work coming in the cash flow.
For eg: I have the BOQ amount for block work.
But there is 45 days gap between solid block work and hollow block work.
After making all the activities related to block work, I connected them all through one hammock and the BOQ amount I given to that hammock as cost.
But when I am loading the cost it will come all days, including the non work period of 45 days. If I can suspend the work for block work, then it is ok.
But in hammock, suspension of work is not possible. Suspension of work is not possible in baseline also.
Without putting the cost for all the activities related to block work by breaking the total BOQ amount for block work; is there anyway to do get the cash flow omitting the non work period?
Pls help
Moosa
For eg: I have the BOQ amount for block work.
But there is 45 days gap between solid block work and hollow block work.
After making all the activities related to block work, I connected them all through one hammock and the BOQ amount I given to that hammock as cost.
But when I am loading the cost it will come all days, including the non work period of 45 days. If I can suspend the work for block work, then it is ok.
But in hammock, suspension of work is not possible. Suspension of work is not possible in baseline also.
Without putting the cost for all the activities related to block work by breaking the total BOQ amount for block work; is there anyway to do get the cash flow omitting the non work period?
Pls help
Moosa
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?