Offshore Instalation

Dattatreya PadharthiMember for 23 years 6 months
Created
2
2
0
Can I get some guidance on factors to be considered while scheduling Subsea Pipeline Construction (> 150 kms), Debottlenecking of (at least 25 Towers/Platforms) & other associated facilities. All lines are existing out of which 150 kms are to be replaced over a period of say 10 years)

thanks
dattatreya

2 replies

Oldest first
  1. 0
    Daniel Limson ·
    Factors to consider on offshore installation works.

    The majority of these type of works are resource driven, meaning your schedule will largely depend on the number of beds you can provide offshore. Your logistics (supply of materials)will also depend on the number of supply boats you have and the distance from the loading pier. All these factors should be worked out in order to get your production rates and determine your duration based on estimated quantities.

    Regards,
    Daniel
  2. 0
    Yousif Alaubidi ·
    Dear all
    thanks for your information on Offshore Instalation , because am working in general company for port of Iraq, can you send me any information or any file that desigen or anaysis by using primavera p3 or any new book on Offshore port

    with me hope for pleature for all

    with best wishes

    Engineer Yousif A.Ayal;
    Iraq
    BNasra
    22/11/2005
    E-mail:yousifalaubidi@yahoo.com

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?