WBS............

Milind PandhareMember for 21 years 1 month
Created
1
2
0
Structure: xxx.xx.xx.xx.x

WBS Code Title

B55 B + G + 7 + H C R E S I ( B - 5 5 )
B55.01 G E N E R A L M I L E S T O N E
B55.02 M A T. & S H O P D R A W I N G
B55.06 S U B S T R U C T U R E
B55.06.01 Mobilisation
B55.06.1 Excavation
B55.06.2 Raft Work
B55.06.3 Basement
B55.07 S U P E R S T R U C T U R E
B55.07.1 Ground Floor
B55.07.1 .A Part -A ( Grid 1-11)
B55.07.1 .B Part -B ( Grid 11-26)
B55.07.2 First FLoor
B55.07.2 .A Part -A
B55.07.2 .B Part -B
B55.07.3 Second FLoor
B55.07.3 .A Part -A
B55.07.3 .B Part -B
B55.07.4 Third Floor
B55.07.4 .A Part -A
B55.07.4 .B Part B
B55.07.5 Fourth Floor
B55.07.5 .A Part -A
B55.07.5 .B Part -B
B55.07.6 Fifth Floor
B55.07.6 .A Part -A
B55.07.6 .B Part -B
B55.07.7 Sixth Floor
B55.07.7 .A Part -A
B55.07.7 .B Part -B
B55.07.8 Seventh Floor
B55.07.8 .A Part -A
B55.07.8 .B Part -B
B55.07.9 Roof Floor
B55.07.91 Upper Roof FLoor
B55.08 I N T E R N A L F I N I S H I N G
B55.08.1 Basement
B55.08.1 .1 Block Work & Plaster
B55.08.1 .2 Flooring Work
B55.08.1 .2 .1 Wet area
B55.08.1 .2 .2 Dry area
B55.08.1 .3 False Ceiling & Painting
B55.08.1 .4 Carpentry & Joinery Work
B55.08.1 .5 Fitting
B55.08.11 Ground Floor
B55.08.11.01 Substation Work
B55.08.11.1 Block Work & Plaster
B55.08.11.2 Flooring Work
B55.08.11.2 .1 Wet area
B55.08.11.2 .2 Dry area
B55.08.11.3 False Ceiling & Painting
B55.08.11.4 Carpentry & Joinery Work
B55.08.11.5 Fitting
B55.08.2 First Floor
B55.08.2 .1 Block Work & Plaster
B55.08.2 .2 Flooring Work
B55.08.2 .2 .1 Wet area
B55.08.2 .2 .2 Dry area
B55.08.2 .3 False Ceiling & Painting
B55.08.2 .4 Carpentry & Joinery Work
B55.08.2 .5 Fitting
B55.08.3 Second Floor
B55.08.3 .1 Block Work & Plaster
B55.08.3 .2 Flooring Work
B55.08.3 .2 .1 Wet area
B55.08.3 .2 .2 Dry area
B55.08.3 .3 False Ceiling & Painting
B55.08.3 .4 Carpentry & Joinery Work
B55.08.3 .5 Fitting
B55.08.4 Third FLoor
B55.08.4 .1 Block Work & Plaster
B55.08.4 .2 Flooring Work
B55.08.4 .2 .1 Wet area
B55.08.4 .2 .2 Dry area
B55.08.4 .3 False Ceiling & Painting
B55.08.4 .4 Carpentry & Joinery Work
B55.08.4 .5 Fitting
B55.08.5 Fourth Floor
B55.08.5 .1 Block Work & Plaster
B55.08.5 .2 Flooring Work
B55.08.5 .2 .1 Wet area
B55.08.5 .2 .2 Dry area
B55.08.5 .3 False Ceiling & Painting
B55.08.5 .4 Carpentry & Joinery Work
B55.08.5 .5 Fitting
B55.08.6 Fifth FLoor
B55.08.6 .1 Block Work & Plaster
B55.08.6 .2 Flooring Work

B55.08.6 .2 .1 Wet area
B55.08.6 .2 .2 Dry area
B55.08.6 .3 False Ceiling & Painting
B55.08.6 .4 Carpentry & Joinery Work
B55.08.6 .5 Fitting
B55.08.7 Sixth Floor
B55.08.7 .1 Block Work & Plaster
B55.08.7 .2 Flooring Work
B55.08.7 .2 .1 Wet area
B55.08.7 .2 .2 Dry area
B55.08.7 .3 False Ceiling & Painting
B55.08.7 .4 Carpentry & Joinery Work
B55.08.7 .5 Fitting
B55.08.8 Seventh Floor
B55.08.8 .1 Block Work & Plaster
B55.08.8 .2 Flooring Work
B55.08.8 .2 .1 Wet area
B55.08.8 .2 .2 Dry area
B55.08.8 .3 False Ceiling & Painting
B55.08.8 .4 Carpentry & Joinery Work
B55.08.8 .5 Fitting
B55.08.9 Roof FLoor
B55.08.9 .1 Block Work & Plaster
B55.08.9 .2 Flooring Work
B55.08.9 .2 .1 Wet area
B55.08.9 .2 .2 Dry area
B55.08.9 .3 Water Proffing Work
B55.08.9 .4 False Ceiling & Painting
B55.08.9 .5 Carpentry & Joinery Work
B55.08.9 .6 Fitting
B55.08.91 Upper Roof Floor
B55.08.91.1 Block Work & Plaster
B55.08.91.2 Flooring Work
B55.08.91.2 .1 Wet area
B55.08.91.2 .2 Dry area
B55.08.91.3 False Ceiling & Painting
B55.08.91.4 Carpentry & Joinery Work
B55.08.91.5
B55.08.91.6
B55.09 H V A C W O R K
B55.09.A Electrical
B55.09.A .1 1st Basement
B55.09.A .2 GF Level
B55.09.A .3 1F Level
B55.09.A .4 2F Level
B55.09.A .5 3F Level
B55.09.A .6 4F Level
B55.09.A .7 5F Level
B55.09.A .8 6F Level
B55.09.A .9 7F Level
B55.09.A .91 RF Level
B55.09.B Plumbing
B55.09.B .1
B55.09.B .2
B55.09.B .3
B55.09.B .4
B55.09.B .5
B55.09.B .6
B55.09.B .7
B55.09.B .8
B55.09.B .9
B55.09.B .91
B55.09.C HVAC
B55.09.C .1
B55.09.C .2
B55.09.C .3
B55.09.C .4
B55.09.C .5
B55.09.C .6
B55.09.C .7
B55.09.C .8
B55.09.C .9
B55.09.C .91
B55.10 E X T E R N A L F I N I S H I N G
B55.10.1 Roof Waterproofing Work
B55.10.A Elevation- A
B55.10.B Elevation -B
B55.10.C Elevation -C
B55.10.D Elevation -D
B55.12 F I N A L F I N I S H I N G
B55.13 P R O V I S I O N A L W O R K
B55.14 T E S T I N G & C O M M I S I O N I N G

1 reply

Oldest first
  1. 0
    Sen Moc ·
    There should be a different category for sample WBS, Schedules, Reports, Estimates, Etc…

    I think it should not be posted here in forums (especially this long) unless it is presented for discussion.

    Could you imagine if a 96,000 activity project, as mentioned by Vlad, will be posted here? Gosh, PP Site storage memory will be full!!!