ACTIVITIES FOR PIPE-RACK ERECTION
In the Open Standard
TD
Ted DaviesMember for 20 years 11 months
- Created
- 14
- 7
0
HI, I WOULD LIKE TO KNOW THE SEQUENCE OF ACTIVITIES RELATED FOR A PIPE-RACK ERECTION, FROM FOUNDATIONS TO THE END, PLEASE. I ALSO WOULD LIKE TO KNOW IN WHAT % COMPLETE YOU START THE FOLLOWING ACTIVITY AND WHAT ACTIVITIES CAN BE START TO START. THANKS IN ADVANCE.
14 replies
Oldest first- 0NANeeraj Agarkar ·Ted,
You could divide the pipe rack length into sections, Section 1, 2 ,3 (generally your piping activities will define these sections).
Within section 1, if you have prefabricated columns and beams, start erection as soon as foundations allow it. otherwise calculate erection starting point from the rate of progress of erection w.r.t to the rate of pouring foundations. You dont want your erection crew idling on account of lack of foundations.
regards
- 0NANeeraj Agarkar ·To answer your second question.. what activities can be start to start :
Only the linkage between starting activites of sections should be Start to Start like
"Section 1 Excavation" (SS+7days) "Section 2 Excavation" as
Finish of section 1 is not related to start of section 2.
All other activites in Pipeprack are of FS nature.
Regards
Neeraj - 0BWBrennan Westworth ·They are good photos
as you can see there are concrete footings, the photo at the bottom appears to be a concrete structure.
Structural Steel:
- columns
- Beams
- Infill Steel
Look at the modularisation, can sections be preassembled off site or away from the workfront?
You would want to put your long runs of pipe in with the structural steel, alternately you could feed it in from the end but this would be the second preference.
Once the pipe is in and fit up its time to weld out.There are published rates for butt welds.
hydrotesting and drying comes next (by the looks of it you are in a Gas plant which is particularly sensitive to moisture). You will need to talk to the gingerbeers to work out test limits and requirements.
Tie in planning is probably the most crucial part of the operation. In an existing plant this will require interface with operations staff to organise isolations.
Hope this helps - 0JGJoel Gilbert ·Brennan,
Got the Photo’s. Pretty much like you described it
Ted,
First photo Total structural steel, can be erected by doing the columns and cross members, and preliminary alignment first. If bib enough crane available then erect the pre-assembled cages and place on columns. Otherwise build in sections as already suggested by Brennan.
Second Photo the white Pipe racks, I can’t see too well it seems it is all-concrete except for the top cage above the 4th level. Or it is also all structural steel but has been fireproofed.
Question of resourcing, your company must have estimated for this project get the man-hours from the project manager and estimate. The estimate should be up into Labor and skilled and give you a good indication.
How many Tons of structural steel has to be erected? in how long a period? How many sufficient tonnage cranes is at your disposal? answers that you must find out.
Hope this helps.
- 0NANeeraj Agarkar ·IMHO, using tender estimates for resourcing is not a good practice.
Your project manager / erection crew can list their preference of resources.
Get quantity estimate from fabrication drawings.
You can use the production rates published in this website to calculate the resource requirements.
For structural steel piperacks, detail planning is required for erection sequence (approach, fabrication output, Crane lift and capacity and methodology etc).
HTH
Neeraj