Piping activities

George BoltonMember for 20 years 11 months
Created
6
2
0
Hi,

I am very interested in learning the logic sequence of piping activities for the construction of oil and gas, from the beginning to the end, and its relationship with structural erection and equipments set-up.

Thank you in advance.

6 replies

Oldest first
  1. 0
    Charleston-Joseph Orbe ·
    Hello George,

    I know this does answer your question.

    How come your in th IT then you find interest in Piping activities.

    I’m just curious.

    Cheers,

    Charlie
  2. 0
    Izam Zakaria ·
    just roughly explaination....

    str
    prefab that’s mean mark cut act. for stiff,plateand etc

    pip
    we’ve
    mark,cut,install,fit,field weld,soft weld,ndt,hydrotest,re-instate and etc..........

    if u want the details act... plaese directly email to me

    aizamcapri@gmail.com or maz.aizam@simedarby.com

    actually i’m very happy with oil and gas industries...
    if compare to design and maintenance side.....
    but is better if u can involve with oil and gas...
  3. 0
    Dilip Konar ·

    Dear Sir, i want total

    Dear Sir,

     i want total process analysis  like pipe ( 2500mm innner dia) manufacturing with 20mm thickness plate including sand blasting and black painting outer surface.

  4. 0
    Mike Testro ·

    Hi DilipExcavaate > Bedding >

    Hi Dilip

    Excavaate > Bedding > String Out > Weld > Test > Cover Joint > Side Lay in Trencg > Backfill 1 > Warning tape > Backfill 2 > FOC > Backfill 3 > Fence / Markers.

    Best regards

    Mike Testro

  5. 0
    Dilip Konar ·

    Dear Sir, i want rate

    Dear Sir,
    i want rate analysis format of pipe manufacturing process.
    like how much manpower, machineries, material required and cosumed enery etc...and testing expenses.

    Thanks

  6. 0
    Jithin Kambhikanam ·

    Hi George,You already have

    Hi George,

    You already have the answer. But let me add mine

    Pipe Delivery - Shop Fabrication - Pipe Fabrication - Pipe Welding - Blasting - Painting - Pipe field Installation Above Ground - Pipelaying on the support - Welding - Hydrotest - For the whole piping at a time-  Leak Test/Nitrogen Flushing 

     