why we generating s- corves in excel??

Aalap ParekhMember for 20 years 11 months
Created
3
3
0
hi all
even though we can generate s- curve in p3 why we use excel to do d same??

3 replies

Oldest first
  1. 0
    Marcio Sampaio ·
    I use excel cose i need to show trend curves and some advertises.
  2. 0
    Joseph Erwin Cargason, C.E.,PSP ·
    Guys,

    How about the value that you are going to use in generating s-curve in excel how can you determine it if u have made your schedule in p3? what are the parameters that you are using to generate the s-curve?

    cheers,

    joseph
  3. 0
    Julie Scully ·
    One of the drawbacks of using P3e is that you cannot view both the early and late curves together, exporting data to excel is a workaround to this issue.

    Cheers
    Julie