Any of you lot had any experience with 4D CAD.

Is it worth the effort, is it just a gimmick, is there any real value added to a project by using it ?

2 replies

Oldest first
  1. 0
    Peter Holroyd ·
    if you mean 3D CAD linked directly to Schedule I am trying to get a thread going under PM Issues

    See http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=5&Top=22897.
  2. 0
    Dana Qandah ·
    I tried to use it once, but the problem is that the one who do planning is usually a civil engineer who is familiar with 2D, but to be able to connect scheduling to 3D, he has to know how to use 3D.

    In my opinion, it is a toy for the client. As the client want to see the progress of the works in a verrrrrrrrrrry simple way.